Affected Activities (Months) Risk Event
1 4.6 C4. System-wide construction staging issues
2 2.5 E9. Delay in PHM 125 approvals
3 1.9 C23. Other construction duration uncertainty (other than identified separately)
4 1.9 D4a. Uncertainty in structure design - municipal replacement structure
5 1.6 D3a. Uncertainty in structure design for one bridge replacement
The risk register is also a tool for monitoring projects from concept to final construction and adjusting expectations along the way. The closer the activity gets to completion, the more certain the management team will be about total costs. Such a risk analysis is an ideal complement to MTO's current Value Engineering and Risk Management processes.
WSDOT's use of probability-based (risk) methods to estimate infrastructure costs has generated considerable interest across
Lastly, by using the results of this process as a communication tool, public officials have been able to demonstrate that they have a process in place for managing public funds. Risk-based cost and schedule analysis allows for identifying, prioritizing and addressing problems before they become major issues, which is one of the best ways to reduce project disruption, cost over-runs, and delays. "WSDOT has performed an unprecedented public service with these latest cost estimates," wrote the Seattle Post-Intelligencer in an editorial in June 2002, "It is a much needed dose of fiscal reality."
No comments:
Post a Comment